Falklands : Question Number 02/2011 by the Honourable Roger Edwards Submitted by Falkland Islands News Network (Juanita Brock) 07.08.2011 (Article Archived on 21.08.2011)
In view of a recent article in the Penguin News and increasing comment from members of the public, please could the Chief Executive give a complete and detailed breakdown of costs of the Container Park built recently close to FIPASS.
Legislative Assembly
Question for Written Answer
Number 02/2011 by the Honourable Roger Edwards
QUESTION NUMBER 02/11 BY THE HONOURABLE ROGER EDWARDS
In view of a recent article in the Penguin News and increasing comment from members of the public, please could the Chief Executive give a complete and detailed breakdown of costs of the Container Park built recently close to FIPASS. Costs are to include preparation works completed by Public Works Department prior to Morrisons getting on site, electrical installations, materials, labour and management costs, concrete and security fence.
Could the Chief Executive also state how much the Falkland Islands Development Corporation put into this project and if this figure is included in the above totals?
Response to Written Question Number 02/11
Spend to date on the container park totals £1,283,000 which is within the approved funding and can be broken down as follows:
FIG costs totalling £468,000 as follows:
Labour costs £ 71,000
Plant Hire costs £106,000
Fuel costs £ 22,000
Plant Maintenance costs £ 17,000
Aggregates £226,000
Asphalt £ 26,000
Costs incurred directly from Morrisons of £441,000 as follows:
Labour & management costs £214,000
Private sector plant hire £ 30,000
Materials costs £100,000
Shipping costs £ 61,000
MFL 10% fee £ 36,000
Other costs, including sub-contractors fees, were incurred as follows:
Concrete works £ 122,000
Electrical works £ 110,000
Floodlights £ 38,000
Fencing costs £ 24,000
Miscellaneous materials £ 21,000
Shipping costs £ 59,000
In addition to this FIDC spent £49,000 on the temporary container yard known as Area A.
Shipping Costs can be broken down as follows:
Morrison’s |
|
|
|
Material |
Shipping Cost |
|
|
Setting out equipment |
£ 260.00 |
Reinforcement Tying Wire |
£ 722.00 |
Bamtec Reinforcing Mat, A393 Mesh & Spacers |
£ 47,414.00 |
Dowels Jointing Materials, Formwork & Concreting Equipment |
£ 10,407.00 |
|
|
Sleepers & Drainage |
£ 2,397.00 |
|
£61,200.00 |
|
|
|
|
Bolt assemblies for floodlights FIC |
£ 404.08 |
Drainage pipes - FIC |
£ 2,766.26 |
Drainage pipes - FIC |
£ 2,921.24 |
Floodlights FIC |
£ 2,964.53 |
Fencing - FIC |
£ 2,593.59 |
Fencing - FIC |
£ 2,933.80 |
Electrical cables - FIC |
£ 2,247.46 |
Concrete shipping costs - SAAS |
£ 29,388.00 |
Electrical materials -AGR |
£ 2,244.92 |
Electrical materials -AGR |
£ 10,191.82 |
|
£58,655.70 |
|